Sidewalk Installation at 2200 Block Bellevue Ave
Friday, April 13, 2012
The Engineering Department will install a sidewalk at the 2200 Block Bellevue Ave as part of the District’s 2012 Road Capital Program.
The construction work began Tuesday, April 10 and is expected to be complete by Friday, April 20, 2012.
The description of work is as follows:
- New 1.5m concrete sidewalk
- Relocation of catchbasins
- Curb bulges
- Existing driveways will be matched into the new sidewalk.
Crews will try to minimize disruption of traffic and pedestrians as much as possible. We apologize for any inconvenience this work may cause.
For additional information about this project, please contact us.
More Information