Nelson Avenue, 6695 (Horseshoe Bay Residences)

Development Application - Approved Applications

May 2022

Buildings 1, 2, 3, and 6 have been issued occupancy permits. The remaining buildings—4, 5, and 7 (amenity building)—are pending occupancy.  

Background

The Horseshoe Bay Residences are a mixed residential and commercial project that includes 159 residential units and 13,700 square feet of commercial area within six buildings and 493 underground parking stalls.

Approved by Council on October 24, 2016, the development is a product of years of community consultation and outreach on the part of Sewell’s, with both official and large-scale (public meeting at Gleneagles Community Centre) and informal (‘coffee klatches’, visioning groups) event formats utilized to garner feedback from a wide variety of local residents.

Construction at the Horseshoe Bay Residences development site has been underway since the spring of 2017.

Construction updates

Project updates about the Horseshoe Bay Residences are posted online at:

Horseshoe Bay Projects

Construction Activities

In accordance with the District's Noise Control Bylaw No. 4404, 2005, construction noise is permitted during the following times:

  • Monday through Friday from 7:30 a.m. to 5:30 p.m.
  • Saturday from 8 a.m. to 5 p.m.
  • no construction noise permitted on Sundays and holidays

Development application and related documents

The approved documents and related background material, reports and superseded versions of the proposal are posted to this page for convenience purposes only.

Summary of the Review Process & Timelines

Phased Development Agreement Authorization Bylaw

Zoning Bylaw Amendment Bylaw

Official Community Plan Bylaw

September 2016 update and documents

A public hearing was held on September 19, 2016, regarding the proposed bylaws. After closing the hearing, Council gave further readings to the bylaws (second and third readings). Prior to bylaw adoption (enactment), the applicant is to fulfil various conditions including the registration of legal agreements. 

Applicant Public Hearing Presentation

Staff Public Hearing Presentation

July 2016 update

At the July 4, 2016, Council meeting, Council rescheduled the Public Hearing for the Sewell's Marina development proposal for September 19, 2016, at 6 p.m.

June 2016 update and documents

Council gave first reading to the proposed bylaws for the Sewell's development proposal at its June 6, 2016, meeting and scheduled a public hearing for July 4, 2016, at 6 p.m. in Council Chamber. Prior to the public hearing, the applicant is hosting a Development Application Information Meeting on June 21, 2016 at the Gleneagles Community Centre (Seaview Room) from 4–7 p.m. At 5 p.m. the applicant will give a presentation on their proposal. This meeting is being held by the applicant to give the public an opportunity to learn about the proposal and ask questions before the scheduled public hearing.

Council Report May 20, 2016

Appendix E OCP Amendment

Appendix F Zoning Amendment

Appendix G Phased Development Agreement Bylaw

Appendix H Master Development Covenant

Appendix I Public Access Covenant

Appendix J Works and Services Agreement

Appendix K Development Permit No 15-037

Schedule A to Development Permit No. 15-037 section A1

Schedule A to Development Permit No. 15-037 section A2

Schedule A to Development Permit No. 15-037 section A3

Schedule A to Development Permit No. 15-037 section A4

Schedule A to Development Permit No. 15-037 section B

Schedule A to Development Permit No. 15-037 section C1

Schedule A to Development Permit No. 15-037 section C2

Schedule A to Development Permit No. 15-037 section C3

Schedule A to Development Permit No. 15-037 section D

March 2016 update and documents:

The Design Review Committee will consider the application (3rd appearance) at its meeting on Thursday, March 17, 2016. The meeting is held in the Council Chamber at Municipal Hall, 750 - 17th Street and starts at 4:30 p.m.

Staff Memo to the Design Review Committee

Sewell's Response to the Design Review Committee

February 2016 update and documents

The development proposal has been revised based on the comments made by the Design Review Committee last September. It is scheduled for reconsideration by the Committee at its meeting on Thursday, February 18, 2016. The meeting starts at 4:30 p.m. in Council Chamber.

Memo to the Design Review Committee - February 2016

September 2015 update and documents

Notification Letter

The District of West Vancouver hosted a series of consultation meetings to familiarize the community with the proposal and to obtain public input.

Drawing Booklet

July 2015 update and documents

Introduced the proposal to Council and advised that information on a community programme would be forthcoming.

July 20, 2015 Council Report

Drawing Booklet

Project highlights are as follows

  • 159 residential units in six buildings, with four levels of underground parking;
  • preliminary building heights between two and nine storeys, with taller buildings nestled toward the adjacent hill;
  • 493 off-street parking spaces, 255 of which are for commercial and marina uses and 238 are for residential use;
  • many different unit floor plans including one bedroom, one bedroom + den or family room, two bedroom, two bedroom + den or family room, three bedroom, and three bedroom + den or family room;
  • a proposed seaside village character, with small squares and a variety circulation options for vehicles and pedestrians; and
  • coordination with the Horseshoe Bay Streetscape Study and the District’s Parks department for consistent streetscape treatment and identification of opportunities for an enhanced waterfront path.