Once your permit has been issued and work completed, it must be inspected.
-
Please note requests received by 8 a.m. Monday to Friday can be completed that day.
-
Forms
An inspection of concrete form work before any concrete being placed on a site. A survey certificate from a BCLS must be on the site showing the location of the forms and include the elevations of any hubs or pour strips. (See WorksafeBC Policy regarding excavation construction site safety)
Slabs
An inspection of the poly and ground preparation under a slab before the placement of any concrete. (Damp-proofing inspections require a Drainage Permit.)
Sheathing
An inspection of the completed exterior sheathing of a building before the installation of any building paper.
Framing
An inspection of the building framework can occur once all framing is completed and only following approval of the rough-in wiring, plumbing, sprinklers and sprinkler insulation. The structural engineer's approval, sealed truss drawings, building envelope consultant's field review and mechanical ventilation checklist must be provided to the building inspector, on-site, at the time of the framing inspection. A survey by a BCLS may be requested at this time to confirm height and siting.
Insulation and Vapour Barrier
An inspection of the thermal insulation and vapour barrier before the installation of any wallboard, panelling or interior finishes. Exterior building paper must be in place before installing the insulation. For new houses, provide a House Performance Report (mid-construction).
-
An inspection which is done once all construction is complete. The final plumbing, sprinkler, radiant heating, drainage and electrical work must be inspected before calling for the final building inspection. Documentation to be provided at the time of final building inspection includes Schedule C-B's from a structural engineer, geotechnical engineer and building envelope consultant, final survey by BCLS showing all buildings and structures, including retaining walls, and final mechanical ventilation checklist.
Final building approval must be received before the building or any portion of the building which has been renovated is occupied.
For new houses, a House Performance Report (as-built) is required.
- BC Energy Step Code
- Complex Buildings – Required Documentation for Final Inspection (PDF)
- Inspections for Commercial Tenant Improvements (PDF)
Final Mechanical Inspection
An inspection after all plumbing fixtures and systems have been installed and are operating with hot and cold water. Learn more about required mechanical inspections.
Final Electrical Inspection
A final electrical inspection is required after completion of all electrical work and will close the permit. Ensure everything is complete, including panel labels, all plates and fixtures are installed, and all exterior electrical work is complete. Note: Every inspection request must be accompanied by a completed declaration form. Learn more about required electrical inspections.